Construct a full steel structure third floor with composite roof deck (reinforced concrete on steel deck) for the high school building at Degla Maadi area, the scope of work covers:
– Prepare existing roof with necessary anchored footings for steel structure in coordination with concrete upgrading sub-phase contractor.
– Fabricate, paint with fire retard, transport and erect steel structure of 150 tons of built-up steel sections, including:
. Columns
. Rafters
. Beams
. Joists
– Steel galvanized roof deck with total area of 1250 square meter.
– Concrete cast for roof deck with total qty of 250 cubic meter of reinforced concrete.
– Embed solar panels anchorage footings into concrete roof deck.
– Handover to last phase contractor for finishing.
Project Type | Steel Structure |
Client | Cairo American College (CAC) |
Completion Date | 2017 |
+2 010 666 588 18
+2 02 33 90 86 38
415, Elgiesh Rd, N Area, Hadabet El Ahram, Giza, Egypt
E-mail:
info@macsegypt.com
MACS was founded in 2014 as a joint stock corporate from the founders and owners of El-Hakim & Partners. Though newly founded, MACS is grounded in industry history based on previous experience of El-Hakim company in both Contracting and Trading.
Follow our latest news and products.